Following Bridges included in Contract No: BU-DSD-19/065/66(Package-19)

  • Project Title : Following Bridges included in Contract No: BU-DSD-19/065/66(Package-19)
  • Employer : Bridge Unit, Department of Roads
  • Year of Completion : 2010
  • Major Components of Services :

    Detailed Engineering Survey, Soil Investigation, Hydrological Study, Detailed Design of Bridge, Detailed Design of approach road, Detailed Design of river training works, cost estimation, 

  • Daram Khola Bridge, Baglung 
  • Madikuwa Shibalaya Bridge, Parbat 
  • Kusma Balewa Hakase Bridge,Parbat 
  • Gaudi Khola Bridge, Baglung 
  • Daram Khola Bridge, Baglung 
  • Bhim Khola Bridge, Baglung 
  • Dowa Bhirkot Bridge, Myagdi 
  • Myagdi Khola Bridge, Myagdi 
  • Girandi Khola Bridge, Baglung